When you first import your alta Common Cartridge into D2L:

  • Your assignments show in the D2L content page within a 'Knewton Coursework' folder.
  • From here, you can edit all of your assignment start and due dates.

If you need to change start or end dates after the course starts and before students start working, you should change them in alta and then also manually change them in D2L.

You can change dates at the parent course outline level to trigger date changes to all child sections, but note that each section instructor will then have to manually alter the dates in D2L.

Question: Will due dates update automatically in D2L if you change them in alta?
Answer: they will not

Question: Will due dates update automatically in alta if you change them in D2L?
Answer: they will not

Did this answer your question?